Foundation and site for a cryogenic tank: a checklist before installation

The most common reason installation slips is not the equipment but the site. Here is what to prepare so the crew works instead of waiting.
Equipment usually arrives on time. What holds a project up is concrete that has not cured, a gate a low-loader cannot pass, or a missing power supply. Everything below can be prepared in parallel with manufacturing, so installation starts the day the tank arrives.
Foundation
- A reinforced concrete slab designed for the weight of the filled tank. For a 30 m³ CO₂ vessel that is roughly forty tonnes together with the product.
- The loads and the support layout come from the supplier with the quotation. Do not pour concrete before you have that drawing — the anchor spacing is not universal.
- Concrete needs time to reach strength. Plan three to four weeks between pouring and installation.
Access and space
- A tanker must reach the filling point within hose distance, normally fifteen to twenty metres, and be able to turn around.
- The area is fenced, with safety distances to buildings, windows and sources of ignition defined by the project and applicable rules.
- Space for the vaporizer next to the tank. Remember that it ices up and drips during defrosting, so no walkway underneath.
Utilities
- Power, if the vaporizer is electric, and for automation and lighting.
- Earthing.
- The pipeline route to the consumer. The shorter and simpler it is, the lower the pressure drop and heat gain.
Documents
Pressure vessels are subject to registration, and installation is carried out by an organisation holding the corresponding permit. Agree in advance who prepares the paperwork — you or the contractor. This is worth settling at the contract stage, because collecting documents afterwards takes longer than the installation itself.
Checklist before the crew arrives
- Foundation poured, cured, dimensions and anchors match the drawing.
- Access road clear, gate width and turning radius checked against the low-loader.
- Crane access and a hard standing for outriggers.
- Power supply brought to the site, earthing loop ready.
- Pipeline route agreed, penetrations through walls made.
- Responsible person on site who can sign for the work.
How long preparation takes
- Layout and load drawing from the supplier — issued with the quotation.
- Design and approvals — from two weeks, depending on the site and who does it.
- Foundation: excavation, reinforcement, pouring — about a week of work.
- Concrete curing — three to four weeks, and this is the part that cannot be compressed.
- Installation and piping — one to two weeks. Commissioning — a few days.
Who is responsible for what
The usual split: the customer prepares the foundation, access, power and the room for the pipeline route; the contractor supplies the equipment, installs it, does the piping, pressure-tests and commissions. Problems start where the boundary is not written down — most often the power supply to the vaporizer and the wall penetrations. Fix both in the contract.
We supply the load diagram and layout together with the commercial proposal, so preparation can start before the contract is signed.
Frequently asked questions
How long does installation take?
For one tank with a vaporizer and piping to a single consumer, typically one to two weeks on site once the foundation is ready, plus commissioning. Multi-tank systems and long pipelines are scheduled individually.
Can a tank be placed indoors?
As a rule, no. Cryogenic vessels vent gas through the safety valve, and in an enclosed space that displaces oxygen. Indoor placement requires a separate project with forced ventilation and oxygen monitoring; the usual solution is an outdoor pad with a canopy.
You may also need



Turnkey installation of cryogenic and gas supply systems
Turnkey installation and commissioning of a cryogenic gas supply system
Model: SRV-INSTALL
Complete installation package for CO₂, N₂, O₂ and Ar systems: tanks, vaporizers, gasifiers, pipelines, reducers, regulators and valves — from foundations tie-in to start-up and operator training.
Price on request
On request





Cryogenic tanks for liquid CO₂ (carbon dioxide) 10–100 m³
Cryogenic tank for liquid CO₂ 30 m³
Model: CT-CO2-30
Stationary vacuum-insulated cryogenic tank for storing liquid CO₂ (carbon dioxide), geometric volume 30 m³. Supplied with valves, pressure control, vaporizers and a pressure-reducing unit; turnkey installation available.
Price on request
Made to order
Related articles

Installation and operation
What makes CO₂ dangerous and what has to be on site because of it
CO₂ is not flammable and not toxic in the usual sense, which is exactly why it gets underestimated. Concentration table, the three real hazards, and the site checklist that closes them.
4 min read
Equipment selection
Rent or buy a cryogenic tank: what the two models really cost
A rented tank looks free until you read the gas price attached to it. A comparison of the three ownership models, the numbers that decide between them, and what «turnkey» has to include.
4 min read
Equipment selection
How to choose the volume of a CO₂ storage tank
An oversized tank ties up money and vents product through the safety valve. An undersized one stops the line when the tanker is late. Here is how to find the middle.
3 min read